O2 Planned Maintenance: Stage 2
Scheduled Maintenance Report for Fonix Services
Completed
The scheduled maintenance has been completed.
Posted Oct 17, 2016 - 06:01 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 16, 2016 - 23:31 BST
Scheduled
Dear Customer

Please see below a communication we have received from O2 regarding planned maintenance on their billing platform on the above date and time.

Please note that Stage 1 was completed as planned but Stage 2 of the below work has been postponed.

Stage 2 was originally scheduled to take place overnight between 22:00 on Sunday 09th October and 06:00 on Monday 10th October but will now take place a week later.

To confirm;

Stage 2 will now take place overnight between 23:30 on Sunday 16th October and 06:00 on Monday 17th October.

The work will have a change window of 22:00 Sunday night to 06:00 on Monday morning and within that window the expected downtime is 2-3 hours beginning at midnight.

During the 2-3 hours downtime it will not be possible to bill O2 post-pay or pre-pay subscribers using premium rate MT SMS. Premium SMS submissions during the platform downtime will be rejected and you would need to re-submit once the work is completed.

Please do not hesitate to contact us if you have any questions.

Kind regards

Fonix Operations Team
Posted Oct 07, 2016 - 15:40 BST
This scheduled maintenance affected: Mobile Operator Connections (O2-UK).